Further to my last post, when i was working the 15th and 16th, the lads came back block laying 1 block layer 1 laborer for the 18,19 & 20th and myself and my father worked there on the 21 & 22nd all the external walls are now complete we have a few internal walls left to do so i am taking tomorrow and Friday off work and myself and my father will hopefully finish it! I have the tracks machine booked for tomorrow also and we will fill the garage base with stone, radon and insulation, we must also move the storage container and open up the permanent site entrance. We are running to a tight schedule in order to have the blocks complete for Monday morning when the carpenters arrive.