Resubmited all the info for the second time this meant that we had to shell out another €120 for site maps as the council apparently dont give them back! But they do refund the value of the planning €65. To cut along story short after a further 2 months recieved a letter from the council stating that they would accept no house on the site only a bungalow of traitional construction. With a roof pitch of less than 36 degrees.
We had to go and design a third house, if this had all been said at the initial pre planning we would have accepted it and got on with the plans for a bungalow. But the council just strung us along this was now our 7th month. We were lucky that i was friends with the engineer so the costs were kept to a minimum. Resubmited all our info once more and to our surprise finally recieved planning three months later.